Balder through the years
Achieved and planned activities and milestones through the years.
2017 | |||
Q1 | Q2 | Q3 | Q4 |
First light in Optics hutch (OH) | First XANES spectrum in OH | Waiting for transfer pipe | Waiting for transfer pipe - arrived in Dec |
2018 | |||
Q1 | Q2 | Q3 | Q4 |
Installation of beam transfer pipe | Awaiting radiation permit | Awaiting radiation permit - granted in September | Commissioning of end station with X-rays |
2019 | |||
Q1 | Q2 | Q3 | Q4 |
Commissioning XAS | Commissioning expert users XAS | - Installation of XES spectrometer during summer shutdown - Regular users XAS | - Regular users XAS - Commissioning XES - Commissioning XRD |
2020 | |||
Q1 | Q2 | Q3 | Q4 |
- User operation XAS | - Installation Cryostat - User operation XAS - Expert users XRD - Comm XES | - Commissioning Cryostat and XES - Summer shutdown | User operation XAS - Installation HR mirror |